Phase 2

Alameda High School

Structural Assessment

  • Estimated Start Date: March, 04 Estimated Finish Date: April, 04
  • Design Time LPA Design Process

  • Estimated Start Date: April, 04 Estimated Finish Date: September, 04
  • DSA Approvals

  • Estimated Start Date: September, 04 Estimated Finish Date: December, 04
  • Bidding

  • Estimated Start Date: December, 04 Estimated Finish Date: January, 05
  • Health & Safety $3,138,000
    Building Shell 776,900
    Building Infrastructure 343,900
    Class Room Renovations 1,948,000
    Support Space Renovations 746,900
    Site Improvements 138,790

    Design Interim Housing

  • Estimated Start Date: August, 04 Estimated Finish Date: October, 04
  • Utilities for Interim Housing

  • Estimated Start Date: October, 04 Estimated Finish Date: October, 04
  • Procure Interim Housing

  • Estimated Start Date: October, 04 Estimated Finish Date: December, 04
  • Install Interim Housing

  • Estimated Start Date: December, 04 Estimated Finish Date: December, 04
  • Install Alarm Devices

  • Estimated Start Date: December, 04 Estimated Finish Date: December, 04
  • Patch Utilities/Ramps

  • Estimated Start Date: December, 04 Estimated Finish Date: December, 04
  • Construction

  • Estimated Start Date: June, 05 Estimated Finish Date: September, 06
  • For the latest progress on initial school projects, please review the Construction Update.

    Back to Construction Home Page

    Back to Measure C Home Page

    Send mail to mikemcmahonausd@yahoo.com with questions or comments about this web site.
    Last modified: March 23, 2004

    Disclaimer: This website is the sole responsibility of Mike McMahon. It does not represent any official opinions, statement of facts or positions of the Alameda Unified School District. Its sole purpose is to disseminate information to interested individuals in the Alameda community.