Phase 1
Chipman Middle School - Two-Story Portables
Update: The supplier for the two story portable could not meet delivery deadlines and subsequently went out of business in Fall, 2004. The portables will be revisited in Spring 2005.
Design Time LPA Design Process
Estimated Start Date: April, 04 Estimated Finish Date: May, 04
DSA Approvals
Estimated Start Date: May, 04 Estimated Finish Date: June, 04
Bidding
Estimated Start Date: June, 04 Estimated Finish Date: July, 04
Construction
Estimated Start Date: July, 04 Estimated Finish Date: September, 04