Phase 1
Lincoln Middle School - Two-Story Portables
Update: The supplier for the two story portable could not meet delivery deadlines and subsequently went out of business in Fall, 2004. The portables will be revisited in Spring 2005.
Design Time LPA Design Process
Estimated Start Date: April, 04 Estimated Finish Date: May, 04
DSA Approvals
Estimated Start Date: May, 04 Estimated Finish Date: June, 04
Bidding
Estimated Start Date: June, 04 Estimated Finish Date: July, 04
Construction
Estimated Start Date: July, 04 Estimated Finish Date: September, 04
Back to Construction Home Page
Back to Measure C Home Page
Send mail to mikemcmahonausd@yahoo.com with
questions or comments about this web site.
Last modified: March 23, 2004
Disclaimer: This website is the sole responsibility of Mike
McMahon. It does not represent any official opinions, statement of facts or
positions of the Alameda Unified School District. Its sole purpose is to
disseminate information to interested individuals in the Alameda community.