Phase 2

New School - Bayport Site

Bayport Site Map

New School Site Plan

New School Courtyard View

Bayport Site Map

NOTE:The dates are educated estimates based prior documentation and will be refined after the structural assessment and design work for the site as well as completion of prior phases. These timetables were prepared in March, 2004.

Design Time LPA Design Process

  • Estimated Start Date: April, 04 Estimated Finish Date: September, 04
  • DSA Approvals

  • Estimated Start Date: September, 04 Estimated Finish Date: February, 05
  • Bidding

  • Estimated Start Date: February, 05 Estimated Finish Date: March, 05
  • Construction

  • Estimated Start Date: April, 05 Estimated Finish Date: September, 06
  • For the latest progress on initial school projects, please review the Construction Update.

    Back to Construction Home Page

    Back to Measure C Home Page

    Send mail to mikemcmahonausd@yahoo.com with questions or comments about this web site.
    Last modified: April 28, 2004

    Disclaimer: This website is the sole responsibility of Mike McMahon. It does not represent any official opinions, statement of facts or positions of the Alameda Unified School District. Its sole purpose is to disseminate information to interested individuals in the Alameda community.