Phase 6
Woodstock Child Development Center
NOTE:The dates are educated estimates based prior documentation and will be refined after the structural assessment and design work for the site as well as completion of prior phases. These timetables were prepared in March, 2004.
Structural Assessment
Estimated Start Date: June, 04 Estimated Finish Date: July, 04
Design Time LPA Design Process
Estimated Start Date: November, 06 Estimated Finish Date: January, 07
DSA Approvals
Estimated Start Date: January, 07 Estimated Finish Date: April, 07
Bidding
Estimated Start Date: April, 07 Estimated Finish Date: May, 07
Design Interim Housing
Estimated Start Date: December, 06 Estimated Finish Date: February, 07
Utilities for Interim Housing
Estimated Start Date: February, 07 Estimated Finish Date: February, 07
Procure Interim Housing
Estimated Start Date: February, 07 Estimated Finish Date: April, 07
Install Interim Housing
Estimated Start Date: April, 07 Estimated Finish Date: April, 07
Install Alarm Devies
Estimated Start Date: April, 07 Estimated Finish Date: April, 07
Patch Utilities/Ramps
Estimated Start Date: April, 07 Estimated Finish Date: April, 07
Construction
Estimated Start Date: May, 07 Estimated Finish Date: July, 07
Back to Construction Home Page
Back to Measure C Home Page
Send mail to mikemcmahonausd@yahoo.com with
questions or comments about this web site.
Last modified: March 23, 2004
Disclaimer: This website is the sole responsibility of Mike
McMahon. It does not represent any official opinions, statement of facts or
positions of the Alameda Unified School District. Its sole purpose is to
disseminate information to interested individuals in the Alameda community.
|