With the successful passage of Measure C in March, 2004, construction can begin on approximately $80+ million in projects. At the Special August 22, 2005 BOE Workshop it became apparent that accelerated construction costs were exceeding budgeted amounts. Staff was directed to prepare revised projections for the Board to reallocate the remaining Measure C funds. Below is their revised projections delivered at the October 11, 2005 BOE meeting.

Measure C 2002 Projections 2005 Revised Projections Expenditures to Date
Phase Two (04/05)
New School - Bayport Site 15,332 19,100 2,013
Alameda New High School 8,000 8,785 828
Lincoln Middle School Renovation 9,410 7,225 1,988
Earhart Elementary 4,000 5,013 1,972
Haight Elementary 3,300 4,362 468
Miller Elementary 1,600 1,590 444
41,642 46,075 7,713
Phase Three (05/06)
Paden Elementary 1,600 1,326 44
Edison Elementary 1,350 1,538 36
Lum Elementary 1,260 1,412 33
Otis Elementary 1,400 1,080 44
Woodstock Elementary 1,440 1,795 95
7,050 7,151 252
Phase Four (06/07)
Washington Elementary 2,300 2,760 193
Longfellow Elementary 1,400 1,283 18
Bay Farm Elementary 1,590 1,376 225
Franklin Elementary 900 430 167
Chipman Middle School Renovation  3,000 1,531 51
9,190 7,380 654
Phase Five (06/07)
Alameda Historic Outer Wings Alameda Historic Middle Wings 12,871 7,000 18
Alameda Adult School 500 630 123
13,371 7,630 141
Phase Six (06/07)
Wood Middle School 3,000 1,380 195
Encinal High School 3,100 3,090 490
Woodstock Child Development Center  250 750 4
6,350 5,220 689
Technology 5,000 5,000 3,900
Furniture, Fixtures and Equipment 2,000 2,000 ?
Interim Housing 3,500 3,500 ?
10,500 10,500 3,900
Total 88,103 83,956 13,349
Expended Costs  3,515
Total Revised with Contingency 87,471

Measure C Financial Activity
Measure C Citizens Oversight Committee Meeting Schedule & Minutes
Measure C Updates to the Board
Send mail to mikemcmahonausd@yahoo.com with questions or comments about this web site.
Last modified: October 9, 2005

Disclaimer: This website is the sole responsibility of Mike McMahon. It does not represent any official opinions, statement of facts or positions of the Alameda Unified School District. Its sole purpose is to disseminate information to interested individuals in the Alameda community.