Staff presented a revised facilities needs at the August 26th BOE meeting and aligned with financing options . Here are the proposed details by site based on high levels estimates prepared in August 2003.

Bay Farm Elementary
Option 3 $1.1 Million
New Playgrounds
Paint Exterior
Upgrade restrooms
New Telephone system
Repair/replace asphlt paving
Repair utilities
Option 2  $4.5 Million Additional Work on Option 3 items plus the following:
Paint Interior
New Doors
New window coverings
Technology
Repair sidewalks
Additional Casework
Option 1 $6.1 Million Additional Work on Option 2 & 3 items plus the following:
Replace Portables
Covered Walkways
HVAC upgrade
Day Care Building
Create classroom near Room 312
Earhart Elementary
Option 3 $2.8 Million
Paint interior/exterior
New playground
Repave play area
Upgrade restrooms
Upgrade landscaping
Upgrade lighting
Modernize utilities
New window coverings
Alarms
Technology
ADA
Structural
Repair roof
Repair/replace windows
Repair/replace doors
Option 2  $4 Million Additional Work on Option 3 items plus the following:
New PA/Clock System
Telephone System
Option 1 $6.7 Million Additional Work on Option 2 & 3 items plus the following:
Upgrade Multiuse Room
Edison Elementary
Option 3 $.4 Million
Upgrade utilities
Upgrade remaining restrooms
Option 2  $1.6 Million Additional Work on Option 3 items plus the following:
Repave asphalt
Upgrade HVAC system
Alarms
Technology
Option 1 $2.1 Million Additional Work on Option 2 & 3 items plus the following:
Repair roof
New PA/Clock system
Franklin Elementary
Option 3 $.3 Million
Repave yard
Upgrade remaining restrooms
Replace window coverings
Option 2  $1.3 Million Additional Work on Option 3 items plus the following:
Upgrade utilities
Alarms
Technology
Option 1 $1.7 Million Additional Work on Option 2 & 3 items plus the following:
Repair/replace windows
Haight Elementary
Option 3 $2.2 Million
Alarms
New window coverings
Paint interior/exterior
Repair HVAC system
Repair roof
Repair/replace windows
Repave play area
Replace floor coverings
Technology
Upgrade lighting
Upgrade restrooms
Upgrade structural as needed
Upgrade utilities
Option 2  $4 Million Additional Work on Option 3 items plus the following:
Do more of what is listed in Option 3
Option 1 $9.5 Million Additional Work on Option 2 & 3 items plus the following:
Remodel Office Area
Longfellow Elementary
Option 3 $.9 Million
Alarms
Replace window coverings
Upgrade remaining restrooms
Option 2  $3.1 Million Additional Work on Option 3 items plus the following:
Upgrade HVAC system
Modernize floor coverings
Technology
Option 1 $4.2 Million Additional Work on Option 2 & 3 items plus the following:
Upgrade Utilities
Upgrade play equipment
Lum Elementary
Option 3 $1.2 Million
Technology
Upgrade floor coverings
Upgrade remaining restrooms
Replace window coverings
Upgrade/modernize utilities
Upgrade Media Center
Option 2  $3.1 Million Additional Work on Option 3 items plus the following:
Repave asphalt
Upgrade landscaping
Technology
Option 1 $4.2 Million Additional Work on Option 2 & 3 items plus the following:
Reapir roof
Upgrade Mulituse room
Upgrade HVAC
MiIler Elementary
Option 3 $1.2 Million
Technology
Upgrade HVAC system
Upgrade remaining restrooms
Repair/Replace Doors
Upgrade lighting
New playgrounds
Upgrade structural as needed
Option 2  $1.5 Million Additional Work on Option 3 items plus the following:
Do more work on items listed in Option 3
Option 1 $1.8 Million Additional Work on Option 2 & 3 items plus the following:
Reapir roof
Upgrade Multiuse room
Upgrade HVAC
Otis Elementary
Option 3 $.6 Million
Upgrade remaining HVAC
Option 2  $2.2 Million Additional Work on Option 3 items plus the following:
Repave asphalt
Upgrade landscaping
Replace window coverings
Alarms
Technology
Option 1 $2.9 Million Additional Work on Option 2 & 3 items plus the following:
Covered walkway to Multi-Purpose Rooms
Repair/Replace windows
Upgrade utilities
Paden Elementary
Option 3 $.7 Million
Replace remaining HVAC
Option 2  $2.9 Million Additional Work on Option 3 items plus the following:
Repair/Replace windows
Repair/Replace floor coverings
Upgrade remaining restrooms
Technology
Option 1 $3.8 Million Additional Work on Option 2 & 3 items plus the following:
Repair roof
Covered walkway to Multi-Purpose room and other classrooms
Upgrade science rooms
Washington Elementary
Option 3 $.5 Million
Repair/Replace windows
Option 2  $1.3 Million Additional Work on Option 3 items plus the following:
Repave asphalt
Replace window coverings
Upgrade remaining restrooms
Alarms
Technology
Option 1 $1.8 Million Additional Work on Option 2 & 3 items plus the following:
Do more work on the items listed in Options 2 & 3
Woodstock Elementary
Option 3 $.4 Million
Upgrade restrooms
Option 2  $1.1 Million Additional Work on Option 3 items plus the following:
Upgarde HVAC
Replace window coverings
Option 1 $1.3 Million Additional Work on Option 2 & 3 items plus the following:
Alarms
Landscape
Technology
Chipman Middle 
Option 3 $.9 Million
Paint interior/exterior
Repave asphalt
Upgrade remaining restrooms
Upgrade HVAC
Repair/replace floor coverings
Option 2  $2.9 Million Additional Work on Option 3 items plus the following:
Modernize utiities
Repair/Replace windows
Upgrade Multiuse Room
Alarms
Technology
Option 1 $3.9 Million Additional Work on Option 2 & 3 items plus the following:
ADA
New Lockers
Upgrade Athletic Facilities
Repair main roof
Replace window coverings
New PA/Clock system
Upgrade science rooms
Upgrade kitchen
Lincoln Middle 
Option 3 $3.6 Million
Paint interior/exterior
Repave asphalt
Modernize restrooms
Upgrade HVAC
Modernize landscaping
ADA
Technology
New PA/clock system
Repair structural as needed
Upgrade lockers/increase quantity
Repair/Replace windows
Repair/Replace window coverings
Upgrade drainage
Option 2  $5 Million Additional Work on Option 3 items plus the following:
Do more work on the Items listed in Option 3
Option 1 $12.5 Million Additional Work on Option 2 & 3 items plus the following:
Upgrade Media Center
Upgrade Multiuse room
Replace portables
Upgrade exterior PE facilities
Wood Middle
Option 3 $.9 Million
Repave asphalt
Upgrade remaining restrooms
Repair/replace floor coverings
Option 2  $3.2 Million Additional Work on Option 3 items plus the following:
Upgrade HVAC system
Repair/Replace windows
Reconfigure Multiuse Room
Alarms
Technology
Option 1 $4.3 Million Additional Work on Option 2 & 3 items plus the following:
Upgrade play field
Alameda High
Option 3 $8 Million
Improve HVAC system
Paint interior/exterior, fix interior hallways
Repave asphalt
Re-landscape school exterior and green space
Modernize swimming pool locker rooms
Modernize all bathrooms
Upgrade utilities
Upgrade lighting
Modernize floor coverings
Upgrade gyms
New windows coverings
Repair windows
Technology
ADA
Option 2  $8 Million No additions
Option 1 $13.2 Million Additional Work on Option 2 & 3 items plus the following:
Upgrade Media Center
Remodel first floor
Upgrade Thompson field
New exterior doors
Repair roof
New PA/Clock system
Encinal High
Option 3 $.9 Million
Repave play area
Light football field
Repair athletic facilities
Replace windows
Replace window coverings
Upgrade telephone/PA/clock/alarm system
Upgrade utilities
Option 2  $3.8 Million Additional Work on Option 3 items plus the following:
Technology
Upgrade exterior landscape
Option 1 $13.2 Million Additional Work on Option 2 & 3 items plus the following:
Upgrade remaining restrooms
Repair/replace track
Upgrade athletic fields
Upgrade kitchen
Island High
Option 1 $.8 Million 
Upgrade utilities
Repair windows
Upgrade restrooms
Repair /Replace doors
Repair HVAC
Adult School
Option 3 $.4 Million
Repair windows
Paint interior
Upgrade landscaping
Option 2  $.5 Million Additional Work on Option 3 items plus the following:
Repair roof
Option 1 $.8 Million Additional Work on Option 2 & 3 items plus the following:
Replace windows
Upgrade Room 100
Historic Alameda High School
Option 3 $10 Million
Repair/Replace boiler
Repair/Replace windows
Repair floors
Upgrade exterior landscape
Seismic upgrade
Classroom technology
Upgrade auditorium
Option 2  $10 Million No changes to Option 3
Option 1  $10 Million No changes to Option 3
Woodstock Child Development Center
Option 3 $.2 Million
Repair/Replace windows
Upgrade HVAC system
New floor coverings
Option 2  $.2 Million No additions to Option 3
Option 1 $.5 Million Additional Work on Option 2 & 3 items plus the following:
Upgrade landscaping
Paint interior/exterior
Upgrade restrooms
New School
Options 1, 2 & 3 are $15 million

[ BACK TO TOP ]

 

   
Send mail to mikemcmahonausd@yahoo.com with questions or comments about this web site.
Last modified: August 30, 2003

Disclaimer: This website is the sole responsibility of Mike McMahon. It does not represent any official opinions, statement of facts or positions of the Alameda Unified School District. Its sole purpose is to disseminate information to interested individuals in the Alameda community.