Bay Farm Elementary |
|
|
|
|
|
|
|
Option 3 $1.1 Million |
|
|
|
|
|
|
|
|
New Playgrounds |
|
|
|
|
|
|
|
Paint Exterior |
|
|
|
|
|
|
|
Upgrade restrooms |
|
|
|
|
|
|
|
New Telephone system |
|
|
|
|
|
|
Repair/replace asphlt paving |
|
|
|
|
|
|
Repair utilities |
|
|
|
|
|
|
Option 2
$4.5 Million Additional Work on Option 3 items plus the
following: |
|
|
|
Paint Interior |
|
|
|
|
|
|
|
New Doors |
|
|
|
|
|
|
|
New window coverings |
|
|
|
|
|
|
Technology |
|
|
|
|
|
|
|
Repair sidewalks |
|
|
|
|
|
|
|
Additional Casework |
|
|
|
|
|
|
Option 1 $6.1 Million
Additional Work on Option 2 & 3 items plus the following: |
|
|
Replace Portables |
|
|
|
|
|
|
|
Covered Walkways |
|
|
|
|
|
|
|
HVAC upgrade |
|
|
|
|
|
|
|
Day Care Building |
|
|
|
|
|
|
|
Create classroom near Room 312 |
|
|
|
|
|
|
|
|
|
|
|
|
Earhart
Elementary |
|
|
|
|
|
|
|
Option 3 $2.8 Million |
|
|
|
|
|
|
|
|
Paint interior/exterior |
|
|
|
|
|
|
|
New playground |
|
|
|
|
|
|
|
Repave play area |
|
|
|
|
|
|
|
Upgrade restrooms |
|
|
|
|
|
|
|
Upgrade landscaping |
|
|
|
|
|
|
|
Upgrade lighting |
|
|
|
|
|
|
|
Modernize utilities |
|
|
|
|
|
|
|
New window coverings |
|
|
|
|
|
|
Alarms |
|
|
|
|
|
|
|
|
Technology |
|
|
|
|
|
|
|
ADA |
|
|
|
|
|
|
|
|
Structural |
|
|
|
|
|
|
|
|
Repair roof |
|
|
|
|
|
|
|
Repair/replace windows |
|
|
|
|
|
|
Repair/replace doors |
|
|
|
|
|
|
Option 2
$4 Million Additional Work on Option 3 items plus the
following: |
|
|
|
New PA/Clock System |
|
|
|
|
|
|
Telephone System |
|
|
|
|
|
|
Option 1 $6.7 Million
Additional Work on Option 2 & 3 items plus the following: |
|
|
Upgrade Multiuse Room |
|
|
|
|
|
|
|
|
|
|
|
|
|
Edison
Elementary |
|
|
|
|
|
|
|
Option 3 $.4 Million |
|
|
|
|
|
|
|
|
Upgrade utilities |
|
|
|
|
|
|
|
Upgrade remaining restrooms |
|
|
|
|
|
Option 2
$1.6 Million Additional Work on Option 3 items plus the
following: |
|
|
|
Repave asphalt |
|
|
|
|
|
|
|
Upgrade HVAC system |
|
|
|
|
|
|
Alarms |
|
|
|
|
|
|
|
|
Technology |
|
|
|
|
|
|
Option 1 $2.1 Million
Additional Work on Option 2 & 3 items plus the following: |
|
|
Repair roof |
|
|
|
|
|
|
|
New PA/Clock system |
|
|
|
|
|
|
|
|
|
|
|
|
|
Franklin
Elementary |
|
|
|
|
|
|
|
Option 3 $.3 Million |
|
|
|
|
|
|
|
|
Repave yard |
|
|
|
|
|
|
|
Upgrade remaining restrooms |
|
|
|
|
|
|
Replace window coverings |
|
|
|
|
|
Option 2
$1.3 Million Additional Work on Option 3 items plus the
following: |
|
|
|
Upgrade utilities |
|
|
|
|
|
|
|
Alarms |
|
|
|
|
|
|
|
|
Technology |
|
|
|
|
|
|
Option 1 $1.7 Million
Additional Work on Option 2 & 3 items plus the following: |
|
|
Repair/replace windows |
|
|
|
|
|
|
|
|
|
|
|
|
|
Haight
Elementary |
|
|
|
|
|
|
|
Option 3 $2.2 Million |
|
|
|
|
|
|
|
|
Alarms |
|
|
|
|
|
|
|
|
New window coverings |
|
|
|
|
|
|
Paint interior/exterior |
|
|
|
|
|
|
|
Repair HVAC system |
|
|
|
|
|
|
Repair roof |
|
|
|
|
|
|
|
Repair/replace windows |
|
|
|
|
|
|
Repave play area |
|
|
|
|
|
|
|
Replace floor coverings |
|
|
|
|
|
|
Technology |
|
|
|
|
|
|
|
Upgrade lighting |
|
|
|
|
|
|
|
Upgrade restrooms |
|
|
|
|
|
|
|
Upgrade structural as needed |
|
|
|
|
|
|
Upgrade utilities |
|
|
|
|
|
|
Option 2
$4 Million Additional Work on Option 3 items plus the
following: |
|
|
|
Do more of what is listed in
Option 3 |
|
|
|
|
Option 1 $9.5 Million Additional
Work on Option 2 & 3 items plus the following: |
|
|
Remodel Office Area |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Longfellow
Elementary |
|
|
|
|
|
|
|
Option 3 $.9 Million |
|
|
|
|
|
|
|
|
Alarms |
|
|
|
|
|
|
|
|
Replace window coverings |
|
|
|
|
|
|
Upgrade remaining restrooms |
|
|
|
|
|
Option 2
$3.1 Million Additional Work on Option 3 items plus the
following: |
|
|
|
Upgrade HVAC system |
|
|
|
|
|
|
Modernize floor coverings |
|
|
|
|
|
|
Technology |
|
|
|
|
|
|
Option 1 $4.2 Million
Additional Work on Option 2 & 3 items plus the following: |
|
|
Upgrade Utilities |
|
|
|
|
|
|
|
Upgrade play equipment |
|
|
|
|
|
|
|
|
|
|
|
|
|
Lum
Elementary |
|
|
|
|
|
|
|
Option 3 $1.2 Million |
|
|
|
|
|
|
|
|
Technology |
|
|
|
|
|
|
|
Upgrade floor coverings |
|
|
|
|
|
|
Upgrade remaining restrooms |
|
|
|
|
|
|
Replace window coverings |
|
|
|
|
|
|
Upgrade/modernize utilities |
|
|
|
|
|
|
Upgrade Media Center |
|
|
|
|
|
Option 2
$3.1 Million Additional Work on Option 3 items plus the
following: |
|
|
|
Repave asphalt |
|
|
|
|
|
|
|
Upgrade landscaping |
|
|
|
|
|
|
|
Technology |
|
|
|
|
|
|
Option 1 $4.2 Million
Additional Work on Option 2 & 3 items plus the following: |
|
|
Reapir roof |
|
|
|
|
|
|
|
Upgrade Mulituse room |
|
|
|
|
|
|
Upgrade HVAC |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
MiIler
Elementary |
|
|
|
|
|
|
|
Option 3 $1.2 Million |
|
|
|
|
|
|
|
|
Technology |
|
|
|
|
|
|
|
Upgrade HVAC system |
|
|
|
|
|
|
Upgrade remaining restrooms |
|
|
|
|
|
|
Repair/Replace Doors |
|
|
|
|
|
|
Upgrade lighting |
|
|
|
|
|
|
|
New playgrounds |
|
|
|
|
|
|
|
Upgrade structural as needed |
|
|
|
|
|
Option 2
$1.5 Million Additional Work on Option 3 items plus the
following: |
|
|
|
Do more work on items listed in
Option 3 |
|
|
|
|
Option 1 $1.8 Million
Additional Work on Option 2 & 3 items plus the following: |
|
|
Reapir roof |
|
|
|
|
|
|
|
Upgrade Multiuse room |
|
|
|
|
|
|
Upgrade HVAC |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Otis
Elementary |
|
|
|
|
|
|
|
Option 3 $.6 Million |
|
|
|
|
|
|
|
|
Upgrade remaining HVAC |
|
|
|
|
|
Option 2
$2.2 Million Additional Work on Option 3 items plus the
following: |
|
|
|
Repave asphalt |
|
|
|
|
|
|
|
Upgrade landscaping |
|
|
|
|
|
|
|
Replace window coverings |
|
|
|
|
|
|
Alarms |
|
|
|
|
|
|
|
|
Technology |
|
|
|
|
|
|
Option 1 $2.9 Million
Additional Work on Option 2 & 3 items plus the following: |
|
|
Covered walkway to Multi-Purpose
Rooms |
|
|
|
|
|
Repair/Replace windows |
|
|
|
|
|
|
Upgrade utilities |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Paden
Elementary |
|
|
|
|
|
|
|
Option 3 $.7 Million |
|
|
|
|
|
|
|
|
Replace remaining HVAC |
|
|
|
|
|
Option 2
$2.9 Million Additional Work on Option 3 items plus the
following: |
|
|
|
Repair/Replace windows |
|
|
|
|
|
|
Repair/Replace floor coverings |
|
|
|
|
|
|
Upgrade remaining restrooms |
|
|
|
|
|
|
Technology |
|
|
|
|
|
|
Option 1 $3.8 Million
Additional Work on Option 2 & 3 items plus the following: |
|
|
Repair roof |
|
|
|
|
|
|
|
Covered walkway to Multi-Purpose
room and other classrooms |
|
|
|
Upgrade science rooms |
|
|
|
|
|
|
|
|
|
|
|
|
|
Washington
Elementary |
|
|
|
|
|
|
|
Option 3 $.5 Million |
|
|
|
|
|
|
|
|
Repair/Replace windows |
|
|
|
|
|
Option 2
$1.3 Million Additional Work on Option 3 items plus the following: |
|
|
|
Repave asphalt |
|
|
|
|
|
|
|
Replace window coverings |
|
|
|
|
|
|
Upgrade remaining restrooms |
|
|
|
|
|
|
Alarms |
|
|
|
|
|
|
|
|
Technology |
|
|
|
|
|
|
Option 1 $1.8 Million Additional
Work on Option 2 & 3 items plus the following: |
|
|
Do more work on the items listed
in Options 2 & 3 |
|
|
|
|
|
|
|
|
|
|
|
Woodstock
Elementary |
|
|
|
|
|
|
|
Option 3 $.4 Million |
|
|
|
|
|
|
|
|
Upgrade restrooms |
|
|
|
|
|
|
Option 2
$1.1 Million Additional Work on Option 3 items plus the
following: |
|
|
|
Upgarde HVAC |
|
|
|
|
|
|
|
Replace window coverings |
|
|
|
|
|
Option 1 $1.3 Million
Additional Work on Option 2 & 3 items plus the following: |
|
|
Alarms |
|
|
|
|
|
|
|
|
Landscape |
|
|
|
|
|
|
|
Technology |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Chipman
Middle |
|
|
|
|
|
|
|
Option 3 $.9 Million |
|
|
|
|
|
|
|
|
Paint interior/exterior |
|
|
|
|
|
|
|
Repave asphalt |
|
|
|
|
|
|
|
Upgrade remaining restrooms |
|
|
|
|
|
|
Upgrade HVAC |
|
|
|
|
|
|
|
Repair/replace floor coverings |
|
|
|
|
|
Option 2
$2.9 Million Additional Work on Option 3 items plus the
following: |
|
|
|
Modernize utiities |
|
|
|
|
|
|
|
Repair/Replace windows |
|
|
|
|
|
|
Upgrade Multiuse Room |
|
|
|
|
|
|
Alarms |
|
|
|
|
|
|
|
|
Technology |
|
|
|
|
|
|
Option 1 $3.9 Million
Additional Work on Option 2 & 3 items plus the following: |
|
|
ADA |
|
|
|
|
|
|
|
|
New Lockers |
|
|
|
|
|
|
|
Upgrade Athletic Facilities |
|
|
|
|
|
|
Repair main roof |
|
|
|
|
|
|
|
Replace window coverings |
|
|
|
|
|
|
New PA/Clock system |
|
|
|
|
|
|
Upgrade science rooms |
|
|
|
|
|
|
Upgrade kitchen |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Lincoln
Middle |
|
|
|
|
|
|
|
|
Option 3 $3.6 Million |
|
|
|
|
|
|
|
|
Paint interior/exterior |
|
|
|
|
|
|
|
Repave asphalt |
|
|
|
|
|
|
|
Modernize restrooms |
|
|
|
|
|
|
|
Upgrade HVAC |
|
|
|
|
|
|
|
Modernize landscaping |
|
|
|
|
|
|
ADA |
|
|
|
|
|
|
|
|
Technology |
|
|
|
|
|
|
|
New PA/clock system |
|
|
|
|
|
|
Repair structural as needed |
|
|
|
|
|
|
Upgrade lockers/increase quantity |
|
|
|
|
|
Repair/Replace windows |
|
|
|
|
|
|
Repair/Replace window coverings |
|
|
|
|
|
Upgrade drainage |
|
|
|
|
|
|
Option 2
$5 Million Additional Work on Option 3 items plus the
following: |
|
|
|
Do more work on the Items listed
in Option 3 |
|
|
|
Option 1 $12.5 Million
Additional Work on Option 2 & 3 items plus the following: |
|
|
Upgrade Media Center |
|
|
|
|
|
|
Upgrade Multiuse room |
|
|
|
|
|
|
Replace portables |
|
|
|
|
|
|
|
Upgrade exterior PE facilities |
|
|
|
|
|
|
|
|
|
|
|
|
|
Wood
Middle |
|
|
|
|
|
|
|
|
Option 3 $.9 Million |
|
|
|
|
|
|
|
|
Repave asphalt |
|
|
|
|
|
|
|
Upgrade remaining restrooms |
|
|
|
|
|
|
Repair/replace floor coverings |
|
|
|
|
|
Option 2
$3.2 Million Additional Work on Option 3 items plus the
following: |
|
|
|
Upgrade HVAC system |
|
|
|
|
|
|
Repair/Replace windows |
|
|
|
|
|
|
Reconfigure Multiuse Room |
|
|
|
|
|
|
Alarms |
|
|
|
|
|
|
|
|
Technology |
|
|
|
|
|
|
Option 1 $4.3 Million
Additional Work on Option 2 & 3 items plus the following: |
|
|
Upgrade play field |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Alameda
High |
|
|
|
|
|
|
|
|
Option 3 $8 Million |
|
|
|
|
|
|
|
|
Improve HVAC system |
|
|
|
|
|
|
Paint interior/exterior, fix
interior hallways |
|
|
|
|
|
Repave asphalt |
|
|
|
|
|
|
|
Re-landscape school exterior and
green space |
|
|
|
|
Modernize swimming pool locker
rooms |
|
|
|
|
|
Modernize all bathrooms |
|
|
|
|
|
|
Upgrade utilities |
|
|
|
|
|
|
|
Upgrade lighting |
|
|
|
|
|
|
|
Modernize floor coverings |
|
|
|
|
|
|
Upgrade gyms |
|
|
|
|
|
|
|
New windows coverings |
|
|
|
|
|
|
Repair windows |
|
|
|
|
|
|
|
Technology |
|
|
|
|
|
|
|
ADA |
|
|
|
|
|
|
|
Option 2
$8 Million No additions |
|
|
|
|
|
Option 1 $13.2 Million
Additional Work on Option 2 & 3 items plus the following: |
|
|
Upgrade Media Center |
|
|
|
|
|
|
Remodel first floor |
|
|
|
|
|
|
|
Upgrade Thompson field |
|
|
|
|
|
|
New exterior doors |
|
|
|
|
|
|
|
Repair roof |
|
|
|
|
|
|
|
New PA/Clock system |
|
|
|
|
|
|
|
|
|
|
|
|
|
Encinal
High |
|
|
|
|
|
|
|
|
Option 3 $.9 Million |
|
|
|
|
|
|
|
|
Repave play area |
|
|
|
|
|
|
|
Light football field |
|
|
|
|
|
|
|
Repair athletic facilities |
|
|
|
|
|
|
Replace windows |
|
|
|
|
|
|
|
Replace window coverings |
|
|
|
|
|
|
Upgrade telephone/PA/clock/alarm
system |
|
|
|
|
|
Upgrade utilities |
|
|
|
|
|
|
Option 2
$3.8 Million Additional Work on Option 3 items plus the
following: |
|
|
|
Technology |
|
|
|
|
|
|
|
Upgrade exterior landscape |
|
|
|
|
|
Option 1 $13.2 Million
Additional Work on Option 2 & 3 items plus the following: |
|
|
Upgrade remaining restrooms |
|
|
|
|
|
|
Repair/replace track |
|
|
|
|
|
|
|
Upgrade athletic fields |
|
|
|
|
|
|
Upgrade kitchen |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Island
High |
|
|
|
|
|
|
|
|
Option
1 $.8 Million |
|
|
|
|
|
|
|
|
Upgrade utilities |
|
|
|
|
|
|
|
Repair windows |
|
|
|
|
|
|
|
Upgrade restrooms |
|
|
|
|
|
|
|
Repair /Replace doors |
|
|
|
|
|
|
Repair HVAC |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Adult
School |
|
|
|
|
|
|
|
|
Option 3 $.4 Million |
|
|
|
|
|
|
|
|
Repair windows |
|
|
|
|
|
|
|
Paint interior |
|
|
|
|
|
|
|
Upgrade landscaping |
|
|
|
|
|
|
Option 2
$.5 Million Additional Work on Option 3 items plus the
following: |
|
|
|
Repair roof |
|
|
|
|
|
|
Option 1 $.8 Million Additional
Work on Option 2 & 3 items plus the following: |
|
|
Replace windows |
|
|
|
|
|
|
|
Upgrade Room 100 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Historic
Alameda High School |
|
|
|
|
|
|
Option 3 $10 Million |
|
|
|
|
|
|
|
|
Repair/Replace boiler |
|
|
|
|
|
|
|
Repair/Replace windows |
|
|
|
|
|
|
Repair floors |
|
|
|
|
|
|
|
Upgrade exterior landscape |
|
|
|
|
|
|
Seismic upgrade |
|
|
|
|
|
|
|
Classroom technology |
|
|
|
|
|
|
Upgrade auditorium |
|
|
|
|
|
|
Option 2
$10 Million No changes to Option 3 |
|
|
|
|
Option 1
$10 Million No changes to Option 3 |
|
|
|
|
|
|
|
|
|
|
|
|
Woodstock
Child Development Center |
|
|
|
|
|
|
Option 3 $.2 Million |
|
|
|
|
|
|
|
|
Repair/Replace windows |
|
|
|
|
|
|
Upgrade HVAC system |
|
|
|
|
|
|
New floor coverings |
|
|
|
|
|
|
Option 2
$.2 Million No additions to Option 3 |
|
|
|
|
Option 1 $.5 Million
Additional Work on Option 2 & 3 items plus the following: |
|
|
Upgrade landscaping |
|
|
|
|
|
|
|
Paint interior/exterior |
|
|
|
|
|
|
|
Upgrade restrooms |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
New
School |
|
|
|
|
|
|
|
|
Options 1, 2 & 3 are $15
million |
|
|
|
|
|